Widow Hill, Burnley
70MW 2 hour system Connection 132kv with ENW Energisation Jun 2025 Battery supplier Samsung SBB EPC LSE/SUIR
70MW 2 hour system Connection 132kv with ENW Energisation Jun 2025 Battery supplier Samsung SBB EPC LSE/SUIR
75% Complete 50 MW 2 hour system Connection 33kv with SSE Energisation Jun 2024 Battery supplier Samsung SDi EPC LS Electric/Suir
Korean press visit and meet. Copy to be supplied
SoloS Power has completed a Framework Agreement to acquire 560MW of battery energy storage projects alongside its partner Shomax Energy Corporation. This will continue SoloS' expansion of interconnected battery projects within the UK and will begin construction of this next phase once they hit shovel-ready status from December 2021.