Winchester
Your Content Goes Here Your Content Goes Here [...]
Your Content Goes Here Your Content Goes Here [...]
Your Content Goes Here Your Content Goes Here [...]
Your Content Goes Here Your Content Goes [...]
70MW 2 hour system Connection 132kv with ENW Energisation Jun 2025 Battery supplier Samsung SBB EPC LSE/SUIR
Your Content Goes Here Your Content Goes Here [...]
75% Complete 50 MW 2 hour system Connection 33kv with SSE Energisation Jun 2024 Battery supplier Samsung SDi EPC LS Electric/Suir
SoloS Power has completed a Framework Agreement to acquire 560MW of battery energy storage projects alongside its partner Shomax Energy Corporation. This will continue SoloS' expansion of interconnected battery projects within the UK and will begin construction of this next phase once they hit shovel-ready status from December 2021.
Registered office:
SoloS Power Limited
Maltravers House
Petters Way
Yeovil, Somerset
BA20 1SH
Contact : info@solospower.com
©Copyright 2024 | SoloS Power Limited | All Rights Reserved